Place Culverts Correctly the First Time
Planning is vital to replace a culvert successfully. If the necessary crew members, equipment, and material are on site, replacing a small culvert is a one-day project. This article will provide information for planning and installing culverts. It is in two parts:
Sizing Pipes Correctly
Culvert Diameter or Cross Section. When an existing culvert has adequately carried
water during heavy storms, the manager can use the same size pipe. If unable to
observe water flow, the manager can ask adjoining landowners about culvert
performance.
Insufficient capacity could be due to prior poor judgment, inadequate installation, or a
changed drainage area. Whatever the cause, more capacity is necessary. If a
larger or modified drainage area is likely in the future, the manager should
consider a larger diameter pipe. When increasing culvert capacity, managers
should consider impacts on adjoining property.
For small diameter culverts, installing two pipes of the same size is often an economical
solution. A qualified person should calculate water volumes, velocities, and
pipe sizes, especially for large capacity culverts. The NHDOT Manual
on Drainage Design for Highways describes this procedure. Analysts should
also consider impacts on upstream and downstream culverts. Finally, mangers
should document the reasons for changing pipe size.
Culvert Length. Pipe length depends on the depth of the culvert. The culvert inlet
should be below the bottom of the road base course. If necessary, crews should
lower the ditch bottom. A metal or plastic culvert should be entirely below the
base course. If that is not possible, managers should consider a concrete
culvert. To determine correct length, managers should
When pipes are too short, water will erode the slope at the end of the pipe. In time, it will erode the road shoulder and traveled way. Frequent inspection is required, and repairs often necessary after each heavy rain. Headwalls are a better solution.
Installation Practices
The following practices will result in a culvert installation that will last many years
Crews should dig a trench wide enough to work alongside the pipe and to compact around it. A
qualified person should determine elevations. Culverts should have a slope along
its length of 1/2 to 1 inch per foot. A hand level is usually sufficient for
this basic surveying.
Qualified personnel should also inspect the foundation soil. Crews should replace poor
material with select material. If a poor foundation is likely, supervisors
should have material readily available. Engineering, including soils analysis,
may be necessary on large pipe installations or in deep fills.
Using hand tools, crews should evenly fine grade the trench bottom to the correct inlet and
outlet elevations. They should shape and compact the bottom in an arc to receive
the pipe.
They can then set the pipe and align it properly. Supervisors should check inlet and outlet
elevations, and record them. They should also record the elevation of the stream
bed or ditch.
The National Corrugated Steel Pipe Association's culvert installation manual states:
Too much emphasis cannot be placed on adequate compaction of backfill. Faulty compaction
has led to more trouble with pipe installation, flexible and rigid, than all
other factors combined."
Crews should backfill only when the pipe is resting firmly on the foundation, and when
heavy rain is unlikely. They should begin with 6-inch lifts of small sized
material. Hand tamping is the best method to compact and seal the backfill
against the lower half of the pipe.
If excavated material is suitable, crews should use it as backfill. Otherwise, they should
use select material. Backfill material must be free of rocks larger than two
inches. Crews should place the material carefully, and compact it evenly in no
more than 8-inch lifts along both sides of the pipe. They should moisten the
materials for compaction, but not so much that it becomes unstable.
Compaction equipment operators should work parallel to the pipe, never against it. They
should not over compact, because the pipe could bend out of alignment. To
achieve adequate cover over a pipe, two or more pipes might be necessary. (See
the Fall 2000 Road Business for multiple culvert installation).
For high velocity and volume water flows, slope protection is usually needed. Flared
ends are cost effective to funnel water into the pipe and to spread outlet flow.
For very high velocity flows, riprap, of a suitable size, is often needed to prevent
erosion.
The goal should be to replace a pipe so it will, with minimum maintenance,
remain in place for its entire life. Managers and crews can achieve this goal by
applying the above information. However difficult to install a culvert
properly, it is more difficult to make major repairs later.
The following books provide information for specific situations:
Manual on Drainage Design for Highways, NHDOT
Drainage, Drainage, Drainage. See page 9
Special thanks to Jerry Ray from HTA for his help with this article.
Source:
Skorseth, Ken. "Place Culverts Correctly the First Time." Special Bulletin #43,
South Dakota Local Transportation Assistance Program, July 2002.
Return to Summer 2003